Concrete Curb & Gutter Calculator

This concrete curb and gutter calculator finds the cubic yards and bags for a curb, or a curb with a gutter. Volume = length × cross-section area, with the cross-section in square inches divided by 144. Enter curb and gutter dimensions, or use a profile from the table.

Written by Maddy · Last reviewed November 1, 2026 · How we calculate

Concrete curb and gutter calculator

100 ft³ · 3.7 yd³ net
Combine a patio, footing and posts into one order.

Order 4.25 yd³ of ready-mix, or 184 bags of 80 lb if a truck cannot reach the pour.

Ready-mix to order
4.25 yd³
Net volume
100.00 ft³ · 3.25 m³ ordered
Cured weight of the pour
15,000 lb · 7.5 tons
With waste (before rounding)
4.07 yd³
80 lb bags
184
60 lb bags
245
50 lb bags
294
40 lb bags
367
Bags cost (80 lb)
$1,196
Ready-mix cost
$758

Default prices are estimates (see cost). Enter your own above for a real comparison.

How to Use the Concrete Curb & Gutter Calculator

  1. Measure the length of the curb run, along its center, in feet. For curves, measure along the curve.
  2. Enter the curb height and width, in inches. For a curb only, set the gutter width to 0.
  3. Enter the gutter width and thickness for curb and gutter.
  4. Read the order. Add waste, because curb forms are slow to set and short pours are common.

Concrete Curb & Gutter Formula

Curb and gutter is a long, constant cross-section. Add the curb area and the gutter area, then multiply by length.

cross-section (sq in) = curb width × curb height + gutter width × gutter thickness

cubic feet = length (ft) × cross-section ÷ 144

cubic yards = cubic feet ÷ 27

  • Curb width and height: The curb section, in inches.
  • Gutter width and thickness: The gutter section, in inches. Use 0 for a curb only.
  • 144: Square inches in a square foot.

Metric: In metric, cross-section in square meters × length in meters = cubic meters. A 150 × 150 mm curb is 0.0225 m².

Worked Example: 100 ft of Curb and Gutter

A 100 ft run of curb and gutter, with a 6 × 6 in curb and an 18 in wide, 6 in thick gutter.

6 × 6 + 18 × 6 = 144 sq in; 100 × 144 ÷ 144 = 100.00 ft³; ÷ 27 = 3.70 yd³

With 10% waste: 4.07 yd³. Order 4.25 yd³ of ready-mix, or 184 bags of 80 lb (245 of 60 lb). Estimated cost at default prices: about $1,196 in 80 lb bags, or $758 ready-mix.

Example Curb and Gutter Profiles: Yards per 100 Linear Feet

Example profiles to show how the cross-section drives the volume. Your municipality or plan sets the real profile, so replace these with its dimensions.

Concrete per 100 linear feet by profile
Profile (example)Cross-section (sq in)yd³ per 100 ft (net)80 lb bags per 100 ft (with waste)
Curb only, 6 in wide × 6 in high360.9346
Curb only, 6 in wide × 12 in high721.8592
Curb and gutter, 6 × 6 in curb + 18 × 6 in gutter1443.70184
Curb and gutter, 6 × 8 in curb + 24 × 8 in gutter2406.17306

Examples only. Standard sections vary by city, county and state.

How Much Concrete for Common Curb Runs

Order size and bags for different lengths of the 6 × 6 in curb with an 18 × 6 in gutter.

How Much Concrete for Common Curb Runs
SizeNet volume (ft³)Order (yd³)80 lb bags60 lb bags
10 ft run10.000.501925
25 ft run25.001.254662
50 ft run50.002.2592123
100 ft run100.004.25184245
200 ft run200.008.25367489
500 ft run500.0020.509171223

Curb Only vs Curb and Gutter

A curb alone is a raised edge that holds soil or directs water. A curb and gutter adds a sloped channel at the base that carries water along the curb. The gutter is usually the larger share of the concrete, so adding one more than doubles the volume of a small curb.

To price a curb only, set the gutter width to 0 in the calculator.

Pouring Curves and Corners

Measure a curved curb along its centerline and divide the work into short sections if the radius changes. Curves use flexible forms, and the real section can differ slightly from the plan. Use the higher waste setting for curves.

Machine-Placed vs Hand-Formed Curbs

Long runs are often placed with a slipform curb machine, while short runs are hand-formed. The concrete volume math is the same. A slipform mix is stiffer, so talk to your supplier about the mix for your method.

Mistakes That Leave You Short

  • Entering the curb and gutter dimensions in feet when the fields are in inches.
  • Measuring the length along the edge of the road instead of along the concrete.
  • Forgetting a thickened section at driveways or ramps.
  • Skipping waste. Long, narrow pours lose concrete at each end of each section.
  • Using an example profile from a table instead of the one on your plan.

See every tool on the all concrete calculators page.

Concrete Curb & Gutter Calculator FAQs

How do you calculate concrete for a curb and gutter?

Add the curb's cross-section area (width × height) to the gutter's (width × thickness), in square inches. Multiply by the length in feet and divide by 144 to get cubic feet, then by 27 for cubic yards. A 144 sq in section over 100 ft is 100.00 ft³, or 3.70 yd³.

How much concrete per linear foot for a curb?

A 6 × 6 inch curb is 36 sq in, so each linear foot holds 0.25 ft³, and 100 feet holds 25 ft³ or 0.93 yd³. A curb and gutter at 144 sq in holds 1 ft³ per linear foot. Use the profile on your plan, because standard sections vary by city.

How many bags of concrete for 100 feet of curb and gutter?

A 144 sq in curb and gutter over 100 ft is 100.00 ft³, so with 10% waste you need about 184 bags of 80 lb. That is 4.25 yd³ of ready-mix, which is the sensible way to buy it at this size.

What is the standard size of a concrete curb?

There is no single standard. Cities, counties and states publish their own curb and gutter sections, and they vary in height, width and gutter width. Get the profile from your plan or the local public works office, then enter its dimensions in the calculator above.

How do I calculate a curved curb?

Measure the length along the curve's centerline, and use that as the length. For a changing radius, split the curve into sections and add them with "Add another section". The cross-section stays the same, so only the length changes. Use extra waste on curves, because forms are harder to set.

Should I use bags or ready-mix for a curb?

A short curb run can use bags, but 100 ft of curb and gutter is 4.07 yd³ and about 184 bags, so ready-mix is practical. Above about 1 yd³ a truck is usually cheaper and faster, if it can reach the run.

Written by Maddy · Last reviewed November 1, 2026 · How we calculate · Report an error