How to Use the Monolithic Slab Calculator
- Measure the length and width of the slab, to the outside of the thickened edge.
- Enter the slab thickness, and the width and total depth of the thickened edge, measured from the top surface.
- Read the order, and check the plan for any interior thickened ribs or load-bearing footings, which are separate sections.
- Order with the allowance from your supplier. Monolithic pours are usually done in one placement.
Monolithic Slab Formula
A monolithic slab is a flat slab with a deeper beam around its edge, formed and poured as one piece.
slab (ft³) = length × width × slab thickness (in) ÷ 12
edge (ft³) = perimeter × edge width (in) ÷ 12 × (edge depth − slab thickness) (in) ÷ 12
cubic yards = (slab + edge) ÷ 27
- Perimeter: 2 × (length + width), in feet.
- Edge width: The width of the thickened edge, in inches.
- Edge depth: The total depth of the edge from the top of the slab, in inches. The slab already covers the first part, so only the extra is added.
Metric: In metric, enter lengths in meters and thicknesses in centimeters converted to meters. The formula is the same, giving cubic meters.
Worked Example: A 30 × 24 ft Shed or Garage Slab
A 30 × 24 ft slab, 4 inches thick, with a 12 inch wide thickened edge that is 12 inches deep.
slab: 30 × 24 × (4 ÷ 12) = 240.00 ft³; edge: 108 × 1 × (8 ÷ 12) = 72.00 ft³; total 312.00 ft³ = 11.56 yd³
With 10% waste: 12.71 yd³. Order 12.75 yd³ of ready-mix, or 572 bags of 80 lb (763 of 60 lb). Estimated cost at default prices: about $3,718 in 80 lb bags, or $1,913 ready-mix.
Monolithic Slab Volumes for Common Building Sizes
Net volume for common slabs, 4 inches thick with a 12 inch wide, 12 inch deep thickened edge. Cubic feet are before waste.
| Building size | Slab (ft³) | Thickened edge (ft³) | Total (ft³) | Order with waste (yd³) |
|---|---|---|---|---|
| 12 × 12 ft | 48.00 | 32.00 | 80.00 | 3.50 |
| 12 × 16 ft | 64.00 | 37.33 | 101.33 | 4.25 |
| 16 × 20 ft | 106.67 | 48.00 | 154.67 | 6.50 |
| 20 × 20 ft | 133.33 | 53.33 | 186.67 | 7.75 |
| 24 × 24 ft | 192.00 | 64.00 | 256.00 | 10.50 |
| 24 × 30 ft | 240.00 | 72.00 | 312.00 | 12.75 |
| 30 × 40 ft | 400.00 | 93.33 | 493.33 | 20.25 |
The edge column is only the extra depth below the slab. Change the edge size in the calculator above for your design.
How Much Concrete as the Edge Size Changes
The same 30 × 24 ft slab with different thickened edges.
| Size | Net volume (ft³) | Order (yd³) | 80 lb bags | 60 lb bags |
|---|---|---|---|---|
| 8 in wide × 8 in deep | 264.00 | 11.00 | 484 | 646 |
| 8 in wide × 12 in deep | 288.00 | 11.75 | 528 | 704 |
| 12 in wide × 12 in deep | 312.00 | 12.75 | 572 | 763 |
| 12 in wide × 16 in deep | 348.00 | 14.25 | 638 | 851 |
| 16 in wide × 16 in deep | 384.00 | 15.75 | 704 | 939 |
| 12 in wide × 24 in deep | 420.00 | 17.25 | 770 | 1027 |
Monolithic vs Separate Footing Pour
In a monolithic pour the footing and slab are placed together, which saves a step and a cold joint between them. In a separate pour, the footing is poured first and the slab later, which is common when the footing must go deep or the walls sit on it.
Which one you can use depends on your soil, frost depth, the structure you are building and local code. Many places allow a monolithic slab for light buildings in mild climates and require separate footings elsewhere. Ask your building department.
Interior Thickened Sections
Plans sometimes add thickened areas under load-bearing walls or posts inside the slab. Those are separate volumes. Add each as its own section using "Add another section", so every part of the pour is counted once.
Base, Vapor Barrier and Reinforcement
A compacted base, a vapor barrier where the plan calls for it, and rebar or mesh are placed before the pour. They do not change the concrete volume, but they decide whether the slab stays flat and dry. Use the rebar calculator for the bars, and follow the plan or engineer.
Mistakes That Leave You Short
- Adding the full edge depth instead of only the part below the slab, which counts the slab twice.
- Forgetting interior thickened sections or footings for posts and walls.
- Using the inside dimensions of the forms for the edge, not the outside.
- Assuming a monolithic slab is allowed everywhere. Frost depth and soil can require separate footings.
- Ordering exactly the calculated volume. Trench edges are rough, so keep a larger allowance.
Related Calculators
- concrete slab calculator
- concrete footing calculator
- rebar calculator
- concrete wall calculator
- concrete slab thickness
See every tool on the all concrete calculators page.
Monolithic Slab Calculator FAQs
What is a monolithic slab?
A monolithic slab is a concrete floor and its footing poured together as one piece. The slab is thin in the middle, usually about 4 inches, and thicker along the edges where the loads go. It saves a separate footing pour, and it is common for sheds, garages and some houses where code allows it.
How do you calculate concrete for a monolithic slab?
Add the slab volume to the extra volume of the thickened edge. The slab is length × width × thickness. The edge is the perimeter × edge width × the depth below the slab. A 30 × 24 ft slab with a 12 × 12 inch edge is 312.00 ft³, or 11.56 yd³ net.
How much concrete for a 30×24 monolithic slab?
With a 4 inch slab and a 12 inch wide, 12 inch deep thickened edge, a 30 × 24 ft slab is 312.00 ft³ net. With 10% waste, order 12.75 yd³ of ready-mix. That is far too many bags to mix, about 572 of 80 lb.
How deep should a monolithic slab edge be?
It depends on your soil, frost depth, building size and local code, so we cannot give one number. Many thickened edges are 12 inches or more from the top of the slab. Ask your building department what is required where you live, and enter that depth in the calculator.
Is a monolithic slab cheaper than a separate footing?
Often, because you pour and finish once, with less formwork and labor. The concrete volume is similar either way, but separate footings add a cold joint and a second pour. Cost still depends on site, soil and code, so get local quotes for both before you decide.
Do I need rebar in a monolithic slab?
Usually yes, especially in the thickened edge, but the requirement comes from your plan, soil and local code. Edge beams often use continuous bars and the slab may use mesh or bars on a grid. Ask your building department or engineer, then count bars with the rebar calculator.
Written by Maddy · Last reviewed November 1, 2026 · How we calculate · Report an error