Concrete Mix Calculator (Cement, Sand & Gravel)

This concrete mix calculator turns a volume of concrete into cement bags, sand and gravel for a mix ratio like 1:2:3 by volume. The dry materials take about 1.54 times the volume of the wet concrete they make, so you buy more material than the pour.

Written by Maddy · Last reviewed November 1, 2026 · How we calculate

Concrete mix calculator

Cement (94 lb bags)
8
Sand
15.2 ft³
Gravel
22.9 ft³
Dry volume to buy
45.7 ft³

Estimate. Assumes dry materials are 1.54 × the wet volume and a 94 lb cement bag is about 1 ft³. Round sand and gravel up.

How to Use the Concrete Mix Calculator

  1. Work out the volume of concrete you need with the concrete calculator, then enter it here in cubic yards or cubic feet.
  2. Pick a ratio by volume. 1:2:3 means 1 part cement, 2 parts sand and 3 parts gravel.
  3. Leave waste at 10% unless your ground is rough. Read cement bags, sand and gravel.
  4. Buy cement in whole bags and sand and gravel by the cubic foot or yard, rounding up.

Concrete Mix Formula

The ratio splits the dry volume into parts. Dry volume is the wet volume times 1.54, because the water and fine particles fill gaps between the aggregate.

dry volume = wet volume × 1.54

cement = dry volume × cement parts ÷ total parts

sand = dry volume × sand parts ÷ total parts

gravel = dry volume × gravel parts ÷ total parts

  • Wet volume: The volume of finished concrete you need, including waste.
  • Parts: The ratio numbers. Total parts is cement + sand + gravel.
  • 1.54: A common dry-to-wet volume factor. Real mixes vary, so treat results as estimates.

Metric: In metric, use cubic meters for the volume. Dry volume is still 1.54 times the wet volume, and a 94 lb (about 42.6 kg) cement bag is about 1 ft³ (0.028 m³).

Worked Example: 1 Cubic Yard at 1:2:3

One cubic yard of concrete mixed from cement, sand and gravel at 1:2:3 by volume.

27 × 1.54 = 41.6 ft³ dry; ÷ 6 parts = 6.93 ft³ per part; cement 6.9 ft³, sand 13.9 ft³, gravel 20.8 ft³

Mix Ratios: Quantities per Cubic Yard

Quantities for one cubic yard of finished concrete, before waste. Cement is shown in cubic feet, and a 94 lb bag is about 1 ft³, so the number is also roughly the bag count. Percentages are by volume and add to 100.

Materials per cubic yard by mix ratio
Ratio (cement : sand : gravel)Cement / sand / gravel (% by volume)Cement (ft³ or about 94 lb bags)Sand (ft³)Gravel (ft³)
1 : 2 : 316.7 / 33.3 / 50.06.913.9 (0.51 yd³)20.8 (0.77 yd³)
1 : 2 : 414.3 / 28.6 / 57.15.911.9 (0.44 yd³)23.8 (0.88 yd³)
1 : 1.5 : 318.2 / 27.3 / 54.57.611.3 (0.42 yd³)22.7 (0.84 yd³)

A 1:2:3 mix is 6 parts, so cement is 1 ÷ 6 = 16.7%, sand 33.3% and gravel 50.0% by volume. A figure like 22 / 33 / 45 does not add up from 1:2:3. Strength depends on water, materials and curing, not on the ratio alone.

Concrete Volumes for Common Small Jobs

Typical small pours, so you can pick the volume to enter above. Multiply the 1 yd³ quantities in the table by the order volume.

Concrete Volumes for Common Small Jobs
SizeNet volume (ft³)Order (yd³)80 lb bags60 lb bags
4 ft × 4 ft pad, 4 in5.330.251014
6 ft × 6 ft pad, 4 in12.000.502230
8 ft × 8 ft pad, 4 in21.331.004053
10 ft × 10 ft pad, 4 in33.331.506282
12 ft × 12 ft pad, 4 in48.002.0088118
3 ft × 20 ft walk, 4 in20.001.003749

Water-Cement Ratio

The water-cement ratio is the weight of water divided by the weight of cement. A lower ratio makes stronger, more durable concrete, and a higher ratio makes it easier to place and weaker. Adding water to make a stiff mix easier to work is the most common way to ruin a batch.

Use only as much water as you need to wet the mix evenly. If a mix is too stiff to place, a small amount of water reducer from your supplier is better than a bucket of water.

Mixing by Hand vs a Mixer

Hand mixing in a wheelbarrow is fine for a few bags. One cubic yard needs about 7 bags of cement at 1:2:3 plus roughly 35 ft³ of sand and gravel, and that is a lot of shoveling. Past about a half yard, rent a drum mixer or order ready-mix.

Mix each batch the same way and for the same time so the whole pour looks and behaves alike. Place it before it starts to set.

Why Pre-Mixed Bags Are Simpler

A bag of pre-mixed concrete already has cement, sand and gravel in the right proportion, so you only add water. The 0.6 ft³ yield of an 80 lb bag makes the quantity math a straight division. Mix from raw cement, sand and gravel when you buy in bulk or need a specific blend. Use the concrete bag calculator when you buy bags.

Mistakes That Leave You Short

  • Treating the ratio as the volume of the pour. A 1:2:3 ratio gives dry parts, and the dry volume is about 1.54 times the finished volume.
  • Mixing parts by weight when the ratio is by volume, or the reverse.
  • Measuring sand by the bucket when it is wet. Wet sand bulks up and throws the ratio off.
  • Adding extra water to make mixing easier, which weakens the concrete.
  • Buying exact quantities with no waste, then coming up short on the last wheelbarrow.

See every tool on the all concrete calculators page.

Concrete Mix Calculator FAQs

How much cement, sand and gravel do I need for 1 cubic yard of concrete?

At a 1:2:3 mix by volume, one cubic yard of finished concrete needs about 6.9 ft³ of cement (about 7 bags of 94 lb), 13.9 ft³ of sand and 20.8 ft³ of gravel. These are estimates, and real mixes vary with materials and moisture.

What does a 1:2:3 concrete ratio mean?

It means 1 part cement, 2 parts sand and 3 parts gravel, measured by volume. That is 6 parts in total, so cement is 16.7% of the dry mix, sand 33.3% and gravel 50%. The ratio sets the proportions of the dry materials, and water is added on top of it.

How many bags of cement are in a cubic yard of concrete?

About 7 bags of 94 lb cement at 1:2:3, about 6 at 1:2:4 and about 8 at 1:1.5:3. A 94 lb bag is roughly 1 ft³, so the cement in cubic feet is also the bag count. These figures use a 1.54 dry-to-wet factor, so treat them as estimates and round up.

Why is dry volume bigger than the concrete I get?

Water and fine particles fill the gaps between the sand and gravel, so the mixed concrete takes up less space than the dry materials did. A common factor is about 1.54, which means 1 yd³ of finished concrete needs about 41.6 ft³ of dry material. This is why you buy more material than the pour.

Is it cheaper to mix concrete myself?

For large volumes, buying cement, sand and gravel in bulk and mixing yourself can cost less than pre-mixed bags, but it takes far more labor and tools. For small jobs, bags are simpler and rarely worth beating on price. Past about a yard, compare against ready-mix, which also saves your back.

How much water do I add to concrete?

Use as little as will wet the mix evenly and let you place it. Water is added by weight relative to cement, and a lower water-cement ratio is stronger and more durable. Follow the instructions on the bag for bagged mix, and avoid adding extra water just to make it easier to move.

Written by Maddy · Last reviewed November 1, 2026 · How we calculate · Report an error